CVD · C-570-059
Certain Cold-Drawn Mechanical Tubing of Carbon and Alloy Steel
Germany, India, Italy, China, South Korea, and Switzerland
Operative Margins
3| Rate | Type | Party |
|---|---|---|
| 21.4% | Likely Margin | Jiangsu Hongyi Steel Pipe Co., Ltd.↳ Jiangsu Hongyi Steel Pipe Co., Ltd............... 21.41 |
| 19.8% | Likely Margin | All-Others↳ All-Others....................................... 19.84 |
| 18.3% | Likely Margin | Zhangjiagang Huacheng Import & Export Co., Ltd.↳ Zhangjiagang Huacheng Import & Export Co., Ltd... 18.27 |
Respondents
0—
Notice Timeline
23| Date | Stage | Outcome | Notice |
|---|---|---|---|
| 2017-05-16 | Initiation | — | 2017-09869 |
| 2017-06-23 | Preliminary | — | 2017-13124 |
| 2017-09-25 | Preliminary | — | 2017-20413 |
| 2017-12-11 | Other | — | 2017-26608 |
| 2018-01-03 | Other | — | 2017-28404 |
| 2018-02-01 | Order | — | 2018-02045 |
| 2019-02-08 | Other | — | 2019-01660 |
| 2019-05-02 | Initiation | — | 2019-08945 |
| 2019-09-09 | Initiation | — | 2019-19417 |
| 2019-09-18 | Other | — | 2019-20179 |
| 2020-02-03 | Other | — | 2020-01977 |
| 2020-04-08 | Initiation | — | 2020-07377 |
| 2020-07-15 | Other | — | 2020-15281 |
| 2021-02-02 | Other | — | 2021-02151 |
| 2021-06-09 | Order | — | 2021-12076 |
| 2022-02-08 | Other | — | 2022-01991 |
| 2023-01-03 | Initiation | — | 2022-28522 |
| 2023-02-02 | Other | — | 2023-02163 |
| 2023-04-03 | Sunset Final | Sunset Continuation Likely | 2023-06793 |
| 2024-02-02 | Other | — | 2024-02113 |
| 2024-02-23 | Continuation | Continued | 2024-03684 |
| 2025-02-03 | Other | — | 2025-02118 |
| 2026-02-02 | Other | — | 2026-02082 |