← Search

CVD · C-570-911

Circular Welded Carbon Quality Steel Pipe

China

Operative Margins

8
RateTypeParty
620.1%Likely MarginTianjin Shuangjie Steel Pipe Co., Ltd.; Tianjin Shuangjie Steel Pipe Group Co., Ltd.; Tianjin Wa Song Imp. & Exp. Co., Ltd.; and Tianjin Shuanglian Galvanizing Products Co., Ltd. (collectively, Shuangjie)Tianjin Shuangjie Steel Pipe Co., Ltd.; Tianjin 620.08 Shuangjie Steel Pipe Group Co., Ltd.; Tianjin
620.1%Likely MarginTianjin Shuangjie Steel Pipe Co., Ltd.; Tianjin Shuangjie Steel Pipe Group Co., Ltd.; Tianjin Wa Song Imp. & Exp. Co., Ltd.; and Tianjin Shuanglian Galvanizing Products Co., Ltd. (collectively, Shuangjie)Tianjin Shuangjie Steel Pipe Co., Ltd.; Tianjin Shuangjie Steel Pipe Group Co., Ltd.; Tianjin Wa Song Imp. & Exp. Co., L
48.2%Likely MarginZhejiang Kingland Pipeline and Technologies Co., Ltd.; Kingland Group Co., Ltd; Beijing Kingland Century Technologies Co.; Zhejiang Kingland Pipeline Industry Co., Ltd.; and Shanxi Kingland Pipeline Co., Ltd. (collectively, Kingland Companies)Zhejiang Kingland Pipeline and Technologies Co., Ltd.; 48.18 Kingland Group Co., Ltd; Beijing Kingland Cent
48.2%Likely MarginZhejiang Kingland Pipeline and Technologies Co., Ltd., Kingland Group Co., Ltd, Beijing Kingland Century Technologies Co., Zhejiang Kingland Pipeline Industry Co., Ltd., and Shanxi Kingland Pipeline Co., Ltd. (collectively, Kingland Companies)Zhejiang Kingland Pipeline and Technologies Co., Ltd., Kingland Group Co., Ltd, Beijing Kingland Century Technologies Co
39.0%All OthersAll OthersAll Others.............................................. 39.01
39.0%Likely MarginAll other producers and exportersAll other producers and exporters....................... 39.01
29.8%Likely MarginWeifang East Steel Pipe Co., Ltd. (East Pipe)Weifang East Steel Pipe Co., Ltd. (East Pipe)........... 29.83
29.8%Likely MarginWeifang East Steel Pipe Co., Ltd. (East Pipe)Weifang East Steel Pipe Co., Ltd. (East Pipe)........... 29.83

Context Look-alikes

excluded · 1
RateTypeParty
Dumping MarginMandatory respondents (East Pipe, Kingland)

Respondents

0

Notice Timeline

29
DateStageOutcomeNotice
2015-05-27Final Determination2015-12786
2015-09-02Initiation2015-21777
2016-02-04Other2016-02151
2016-09-12Initiation2016-21866
2016-12-21Other2016-30727
2017-09-13Initiation2017-19417
2017-10-19Other2017-22685
2018-07-03Other2018-14263
2018-09-10Initiation2018-19570
2018-10-01Other2018-21294
2018-11-01Initiation2018-23875
2019-03-25Sunset FinalSunset Continuation Likely2019-05646
2019-04-11Other2019-07196
2019-06-26ContinuationContinued2019-13617
2019-09-09Initiation2019-19417
2019-10-30Other2019-23683
2020-07-01Other2020-14195
2022-07-01Other2022-14126
2022-08-04Initiation2022-16715
2023-04-12Preliminary2023-07726
2023-10-10Scope Ruling2023-22408
2023-11-09Order2023-24806
2024-04-01Other2024-06834
2024-05-01Initiation2024-09424
2024-09-09Sunset FinalSunset Continuation Likely2024-20205
2024-11-19Initiation2024-26890
2024-12-31ContinuationContinued2024-31411
2025-07-22Preliminary2025-13787
2026-02-03Order2026-02104